Rail Yard Capacity Modeling

Client:




Aurizon is an Australia’s largest rail freight operator, managing more than 700 locomotives and more than 16,000 wagons. Aurizon is widely engaged in coal, iron ore, and mineral transportation. The company is the world’s largest rail transporter of export coal from mine to port. In order to increase operational efficiency the company decided to move one of their rail yards to other town. This rail yard was mainly engaged in wagon and locomotive maintenance and locomotive preparation.


Problem:




Aurizon approached Evans & Peck consulting company with the following task:

  • To determine the capacity of a rail maintenance yard and if additional roads were required when additional services were moved to the yard.
  • To develop the model in a relativity short time when compared to current modelling methods used at Aurizon.
  • To build a model which can be reused in a larger network model if required.

Solution:




Rail yard 2DThe consultants employed AnyLogic’s Rail Yard Library for simulating operations within the rail yard (including locomotive preparation, locomotive maintenance, wagon maintenance, reliability examinations of trains, wagon stowage, locomotive stowage and passing traffic). They had to construct the model in a modular fashion to allow components to be reused and the yard model to be connected / incorporated into other models.

The model permitted the testing of the following:

  • Train configurations
  • Train movements within the yard
  • Track utilisation
  • Facility utilisation
  • Stowage times within the yards
  • Scheduling of activities
  • Impact on mainline services

The model is a good demonstration of AnyLogic’s ability to build complex models without extensive Java coding.


Results:




Rail Yard 3D The model was used to determine:

  1. If additional roads were required within the rail yard
  2. If operations at surrounding yards could be moved to the yard in question
  3. What effect the shifting of these operations had on the Train Master Plan
  4. How activities can be coordinated better within the yard

The model was constructed in a way that allows it to be placed into a larger network model, which Aurizon is developing with the assistance of Evans & Peck.


Watch Martin van Holten from Evans & Peck presenting this project in detail at The AnyLogic Conference 2012 or download his presentation:



More Case Studies

  • Selecting the Best Inventory Policy Using Gojii
    Existing supply chain and S&OP tool sets do a great job of managing supply to meet a selected "forecast." However, there is no single "correct forecast" of future demand, and existing tools are not designed to select the best demand level for the business. There is a "tool gap" between forecast inputs and selection of the best demand signal (aka "forecast") to drive your S&OP system. Gojii is the tool created by DecisioTech that fills that gap.
  • Maximizing Push Boat Fleet’s Net Voyage Revenue
    InterBarge, a first-class waterway operator, affiliated with SCF Marine, a part of Seacor Holding Group, operates freight along the HPP Waterway (Hidrovia Parana Paraguay, located in Argentina, Paraguay, Brazil, and Uruguay) on a dedicated contract carriage. The company’s challenge was to use the boat capacity free from dedicated contract commitment as a fleet, maximizing net voyage revenue.
  • Customer-Centric Transportation Network Modelling
    The public transportation company employed PwC Australia to develop a solution that could provide a customer-centric view of their railway infrastructure and help the company understand the current incident effects on rail network operations and how to improve the situation. PwC consultants decided to build a model of the transportation network that would simulate train movements, incidents, and customers at stations and in trains.
  • CSX Solves Railroad Operation Challenges with and without AnyLogic Rail Library
    CSX is a US railroad company that operates about 21,000 route miles (34,000 km). AnyLogic allows the railroad industry users to simulate line-of-road, terminal, and yard problems. The following three projects, completed by CSX in 2014, covered a variety of tasks that were solved using AnyLogic software.
  • Preventing “Bus Bunching” with Smart Phone Application Implementation
    In public transport, bus bunching refers to a group of two or more transit vehicles (such as buses or trains), which were scheduled to be evenly spaced running along the same route, instead running in the same location at the same time. Dave Sprogis, Volunteer Software Developer, and Data Analyst in Watertown, MA, used AnyLogic to confirm his thesis that preventing "Bus Bunching" would improve the experience of public transit bus riders.
  • Emergency Evacuation Planning: Minimizing Gridlock and Improving Public Safety
    A typical rush hour impedes the mobility of individual vehicles and significantly slows the overall flow of traffic. This phenomenon is compounded by events of mass mobilization, such as during an evacuation due to a hurricane or other event. When this occurs, traffic can reach a state of gridlock. ITS researchers sought to understand how public safety could be improved during such events by incorporating communication among a percentage of the vehicle population.
  • Supply Chain Design for Vaccine Manufacturer
    GlaxoSmithKline (GSK) was the world’s sixth largest pharmaceutical company in 2014. The company was launching a new vaccine product on a new market that needed a distribution network different from what they had before. Therefore, the company needed to design a new supply chain and align manufacturing processes with it.
  • Apparel Company Chose Location for New Distribution Center Using Simulation Modeling
    Fruit of the Loom (FOTL) is one of the largest US apparel manufacturers and marketers. The company was expanding, and the executives wanted to know if it would be beneficial, in terms of shipping costs, to add a new distribution center (DC) on the east/west coasts of the US, or to redistribute products to a pre-existing DC. The contractors decided to simulate the whole supply chain in order to visualize DC locations on a GIS map, and the supply network between them.
  • Improving Mining Outbound Logistics with Agent-Based Simulation Modeling
    One of the largest resource companies in the world, with over $80 billion in sales, decided to enter a new market. It was planning to build a new potash mine with 90% of the resources exported. They wanted to design a reliable supply chain, with a high speed of supply replenishing, and the ability to recover from natural disasters and man-made crises benefiting from such volatility. Amalgama and Goldratt companies contracted this project to design the potash mining operations and a full supply chain of outbound logistics.
  • Simulation of the Construction of a Tunnel with a Tunnel Boring Machine
    The cost of one hour of down time of a tunnel boring machine is usually high and project managers have to do their best to avoid unnecessary delays in construction. The aim of the simulation project, which was carried out at Ruhr University Bochum in Germany, was to create a simulation model that would be capable of determining the bottlenecks in tunnel building processes in order to minimize the possible monetary losses.